DILLINGHAM: Airport Needs List

Base Information
Owner: ALASKA DOT&PF CENTRAL REGION
NPIAS: 02-0078
Airport Use: Public
Type: Airport
FAA Associated City: DILLINGHAM
DOT&PF Region: Central
DOT Owned: True
Facility Status: Active
Filter +/-
Needs Funding Source:
Status:
Need Category:
M&O Activity:
 
ASAP Needs Total:   Short Term Needs Total:
Mid Term Needs Total: Long Term Needs Total:
All Needs Total: Needs in Project Total:
Number of Needs: Number of Needs in Project:
 
Needs List
NeedsPriorityNeed OriginationFunding SourceStatusEstimated CostLast Edit DateLast Verified Date
Acquire New Loader Acquire New Loader Short M&O AIP In Project $562,500 1/20/2023 
Acquire Plow Truck w/Belly Blade & Sander Acquire Plow Truck w/Belly Blade & Sander Mid M&O AIP In Project $400,000 3/3/2023 
Acquire replacement water rescue rafts Acquire replacement water rescue rafts Short Letter of Compliance AIP In Project $36,392 3/17/2021 
Acquire Truck (to Tow Broom) Acquire Truck (to Tow Broom) Mid M&O AIP In Project $400,000 3/3/2023 
Construct Runway Construct Runway Short ALP/Master Plan AIP In Project $48,559,600 10/5/2023 
Construct Runway Lighting Construct Runway Lighting Short ALP/Master Plan AIP In Project $2,236,400 10/5/2023 
Construct Service Road Construct Service Road Short Letter of Compliance AIP In Project $15,818,814 9/13/2021 
Construct Taxiway Construct Taxiway Short ALP/Master Plan AIP In Project $20,875,600 10/5/2023 
Construct Taxiway Embankment Construct Taxiway Embankment Short ALP/Master Plan AIP In Project $9,675,500 10/5/2023 
Construct Taxiway Lighting Construct Taxiway Lighting Short ALP/Master Plan AIP In Project $2,346,400 10/5/2023 
Crack Seal Crack Seal Short Other AIP In Project $75,323 1/26/2022 
De-icer Truck 4,000 gal De-icer Truck 4,000 gal Short Other AIP In Project $360,599 4/19/2021 
Install Vertical / Visual Guidance System Install Vertical / Visual Guidance System Short ALP/Master Plan AIP In Project $11,009,500 10/5/2023 
Land Acquisition - Runway Land Acquisition - Runway Short ALP/Master Plan AIP In Project $4,078,800 10/5/2023 
Land Acquisition - Taxiway Land Acquisition - Taxiway Short ALP/Master Plan AIP In Project $152,500 10/5/2023 
Obstruction Removal Obstruction Removal Short ALP/Master Plan AIP In Project $1,755,200 10/5/2023 
Pavement Markings Pavement Markings Short Other AIP In Project $173,987 1/26/2022 
Purchase AFFF Testing Equipment Purchase AFFF Testing Equipment ASAP Other AIP In Project $56,836 3/22/2021 
Reconstruct Perimeter Fencing required by 49 CFR 1542 Reconstruct Perimeter Fencing required by 49 CFR 1542 Short Letter of Compliance AIP In Project $1,474,885 9/13/2021 
Rehabilitate Apron Rehabilitate Apron Short ALP/Master Plan AIP In Project $3,205,051 10/5/2023 
Rehabilitate Runway Safety Area Rehabilitate Runway Safety Area Short ALP/Master Plan AIP In Project $7,223,100 10/5/2023 
Replace Towed Runway Broom 39300 Replace Towed Runway Broom 39300 Mid M&O AIP In Project $600,000 3/3/2023 
Update Airport Master Plan Update Airport Master Plan Short Other AIP In Project $154,500 2/12/2021 
Construct an FAA-compliant RSA Construct an FAA-compliant RSA N/A FAA Initiatives AIP Need Created $0 6/3/2015 
Install Continuously Operating Reference Stations (CORS) Install Continuously Operating Reference Stations (CORS) Short Sponsor Stimulus Need Created $75,000 3/24/2022 
      Total