Base Information
Owner: STATE OF ALASKA DOTPF
NPIAS: 02-0016
Airport Use: Public
Type: Airport
FAA Associated City: ANCHORAGE
DOT&PF Region: Central
DOT Owned: True
Facility Status: Active
Filter +/-
Needs Funding Source:
Status:
Need Category:
M&O Activity:
 
ASAP Needs Total:   Short Term Needs Total:
Mid Term Needs Total: Long Term Needs Total:
All Needs Total: Needs in Project Total:
Number of Needs: Number of Needs in Project:
 
Needs List
NeedsPriorityNeed OriginationFunding SourceStatusEstimated CostLast Edit Date
ANC - Construct Perimeter Road Short Sponsor Stimulus In Project $2,000,000 2/12/2024
ANC - Install Visual Paging System (ADA compliance) Short FAA Initiatives Stimulus In Project $2,100,000 2/9/2024
ANC - Part 150 Noise Compatibility Study Short Sponsor N/A In Project $2,500,000 2/12/2024
ANC - Rehabilitate Kilo Tug Road – Drainage Short Other AIP In Project $5,000,000 2/9/2024
ANC - Rehabilitate Kilo Tug Road – Rehabilitation Short M&O AIP In Project $1,700,000 2/9/2024
ANC - Rehabilitate Taxilane Short M&O AIP In Project $300,000 2/9/2024
ANC 2021 Master Plan Update Short ALP/Master Plan AIP In Project $3,500,000 11/29/2022
ANC Airport Sustainability Plan Mid FAA Initiatives N/A In Project $1,500,000 11/3/2023
ANC ARFF - Acquire Two 3000 Gallon Airport Rescue and Firefighting (ARFF) Trucks Mid Other AIP In Project $2,115,000 2/9/2024
ANC Improve Runway 7L/25R Lighting Duct Drainage Short Sponsor AIP In Project $1,600,000 2/12/2024
ANC NT - Install Taxiway Lighting Short M&O AIP In Project $792,800 2/12/2024
ANC NT - Reconstruct North Terminal Gates Apron N1, N3, N5, & N7 Short M&O AIP In Project $19,638,500 2/12/2024
ANC NT - Reconstruct North Terminal North Taxilane N/A M&O AIP In Project $5,557,900 2/12/2024
ANC PBB - Replace Passenger Boarding Bridge at the North Terminal ASAP Other Stimulus In Project $3,500,000 2/9/2024
ANC PBB - Replace Passenger Boarding Bridges - B4/N3 ASAP Other AIP In Project $5,875,000 2/12/2024
ANC Rehabilitate Aprons - Gates N2 & N4 Mid Other AIP In Project $3,500,000 2/12/2024
ANC Rehabilitate Aprons - Papa 1-3 Short Other AIP In Project $3,000,000 2/9/2024
ANC Rehabilitate Aprons - RON 12-14 Mid Other AIP In Project $3,000,000 2/13/2024
ANC Rehabilitate Aprons - RON 2 Short M&O AIP In Project $800,000 2/13/2024
ANC Rehabilitate Aprons - RON 3-4 Short M&O AIP In Project $3,000,000 2/13/2024
ANC Rehabilitate Aprons - RON 7-11 Short Other AIP In Project $5,000,000 2/13/2024
ANC Rehabilitate Outfall D Mid Other AIP In Project $6,139,471 2/13/2024
ANC Security Fencing Installation M&O AIP In Project $600,000 2/12/2024
ANC SRE Acquisitions for FFY 2025 Mid Other AIP In Project $2,263,050 2/13/2024
ANC SRE Acquisitions for FFY 2026 Mid Other AIP In Project $2,421,463 2/13/2024
ANC Taxiway K & R - Rehabilitate Taxiway K and R Intersection Mid Other AIP In Project $3,000,000 2/12/2024
ANC Taxiway R South & L - Improve Airport Drainage Mid Other AIP In Project $1,140,000 2/14/2024
ANC Taxiway R South & L - Rehabilitate Taxiway Mid Other AIP In Project $14,490,239 2/14/2024
ANC Taxiway R South & L - Taxiway Lighting Mid Other AIP In Project $2,575,000 2/14/2024
ANC TL E - Improve Airport Drainage Short Inspection AIP In Project $3,557,000 2/9/2024
ANC TL E - Reconstruct Taxiway Lighting Short Inspection AIP In Project $2,870,000 2/9/2024
ANC TL E - Rehabilitate Taxilane Short Inspection AIP In Project $18,941,000 2/9/2024
ANC TL P - Rehabilitate Taxilane Papa Mid Other AIP In Project $3,000,000 2/9/2024
ANC TL T - Rehabilitate Taxilane Tango Mid Other AIP In Project $10,000,000 2/9/2024
ANC TW R - Improve Airport Drainage N/A Other AIP In Project $5,951,000 2/12/2024
ANC Water Main - Rehabilitate Terminal Building Short M&O AIP In Project $14,601,274 2/12/2024
Equipment 2023 N/A Other AIP In Project $2,860,466 11/29/2022
Extend TW Zulu West Short ALP/Master Plan AIP In Project $23,200,000 10/20/2022
Improve TW Z West Short ALP/Master Plan AIP In Project $24,200,000 10/20/2022
Install Lighting TW Zulu West Short ALP/Master Plan AIP In Project $300,000 10/20/2022
Rehabilitate Sand and Chemical Storage Building Short M&O AIP In Project $2,500,000 11/30/2022
Rehabilitate Taxilane Short M&O AIP In Project $1,500,000 11/30/2022
Rehabilitate Taxilane - Drainage Short M&O AIP In Project $500,000 11/30/2022
Rehabilitate TW K & TL E Apron Short Sponsor AIP In Project $3,500,000 11/16/2022
Rehabilitate TW K & TL E Apron - Drainage Short Sponsor AIP In Project $500,000 11/16/2022
Replace Passenger Boarding Bridge Short M&O AIP In Project $2,400,000 12/5/2022
Replace Passenger Boarding Bridge N7 Short M&O AIP In Project $3,485,643 11/30/2022
TSA Passenger Screening Expansion Mid ALP/Master Plan N/A In Project $20,000,000 11/3/2023
TW R North - Reconstruct Taxiway Lighting (centerline lights) Short Other AIP In Project $2,599,000 1/31/2024
TW R North - Reconstruct Taxiway Lighting (edge lights) Short M&O AIP In Project $980,000 1/31/2024
TW R North - Rehabilitate Taxiway Short M&O AIP In Project $10,629,000 1/31/2024
TW Z East - Construct new entrance TL to Kulis Apron Short ALP/Master Plan AIP In Project $2,308,853 2/9/2024
TW Z East - Extend TW Z (East to RW 25L end via TW C) Short ALP/Master Plan AIP In Project $25,184,060 2/9/2024
TW Z East - Modify Service Road (Realign service road around AOA) Short ALP/Master Plan AIP In Project $8,465,794 2/9/2024
TW Z East - Reconfigure Existing Kulis Apron Short ALP/Master Plan AIP In Project $48,230,648 2/9/2024
TW Z East - Reconfigure Existing TL C Short ALP/Master Plan AIP In Project $2,308,853 2/9/2024
TW Z East - Reconfigure Existing TW C (Perpendicular to RW 7R/25L) Short ALP/Master Plan AIP In Project $6,975,861 2/9/2024
TW Z East - Reconstruct Perimeter Fencing required by 49 CFR 1542 Short ALP/Master Plan AIP In Project $1,723,819 2/9/2024
TW Z West Ext P1 - Construct Taxiway Short ALP/Master Plan AIP In Project $15,000,000 2/9/2024
TW Z West Ext P1 - Extend Taxiway Mid ALP/Master Plan AIP In Project $25,117,000 2/9/2024
Upgrade BHS ASAP Sponsor Stimulus In Project $1,341,652 6/27/2023
Visual Paging System Installation Short Community Stimulus In Project $2,100,000 10/26/2023
Improve Airport Drainage Short M&O AIP Need Created $1,140,000 11/30/2022
Reconstruct Kilo Tug Road - Drainage Short M&O AIP Need Created $300,000 11/29/2022
      Total