Need Name:
Construct Taxiway Embankment
Type:
AIP/M&O AIP
Community/Economic Development
Funding Source:
Select One
State GF
AIP
M&O AIP
M&O Operating
Stimulus
Local
Bond
N/A
Category:
Select One
APRON
BUILDING
EQUIPMENT
FENCING
GROUND TRANSPORTATION
HELIPAD
LEASING
NEW AIRPORT
OTHER
PLANNING
RUNWAY
SEAPLANE BASE
TAXIWAY
Sub Category:
Select One
Construct Taxiway
Demolish Taxiway
Extend Taxiway
Install Taxiway Lighting
Install Taxiway Sensors
Rehabilitate Taxiway
Rehabilitate Taxiway Lighting
Relocate Taxiway
Strengthen Taxiway
Widen Taxiway
Estimated Cost:
$9,675,500
Description:
Construct partial parallel taxiway and taxiway A and B embankment with surcharge.
Priority:
Short
Need Origination:
ALP/Master Plan
Select One
5010
ALP/Master Plan
Community
FAA Initiatives
Inspection
Letter of Compliance
M&O
Other
Sponsor
State Equipment Fleet (SEF)
Justification:
The runway is being shifted 150 feet toward the apron. Partial parallel taxiway will be constructed to mitigate line of sight. All taxiways must be compatible with the new runway configuration. Embankment will require settlement prior to pavement.
Notes:
ST, TW, CO
Last Edit Date:
10/5/2023 01:59 PM
History Log
Rebecca Douglas
Need Created
6/8/2023 07:33 AM
Rebecca Douglas
In Project
6/8/2023 07:38 AM
Philana Miles
Need Created
9/20/2023 02:22 PM
Removed from project.
Philana Miles
In Project
10/5/2023 04:01 PM