Need Overview
Need Name:
ANC Water Main - Rehabilitate Terminal Building
Type:
AIP/M&O AIP
Community/Economic Development
Funding Source:
Select One
State GF
AIP
M&O AIP
M&O Operating
Stimulus
Local
Bond
N/A
Category:
Select One
APRON
BUILDING
EQUIPMENT
FENCING
GROUND TRANSPORTATION
HELIPAD
LEASING
NEW AIRPORT
OTHER
PLANNING
RUNWAY
SEAPLANE BASE
TAXIWAY
Sub Category:
Select One
Acquire Handicap Passenger Lift Device
Construct ARFF Building
Construct Building
Construct Passenger Shelter
Construct Sand and Chemical Storage Building
Construct SREB
Construct Terminal Building
Construct Toilet Facilities
Demolish Building
Expand ARFF Building
Expand Building
Expand Sand and Chemical Storage Building
Expand SREB
Expand Terminal Building
Hazmat Removal
Improve ARFF Building
Improve Building
Improve Sand and Chemical Storage Building
Improve SREB
Improve Terminal Building
Modify ARFF Building
Modify Building
Modify Sand and Chemical Storage Building
Modify SREB
Rehabilitate ARFF Building
Rehabilitate Building
Rehabilitate Sand and Chemical Storage Building
Rehabilitate SREB
Relocate Building
Estimated Cost:
$14,601,274
Description:
Improve approximately 6,000 feet of existing water mains by trenchless techniques that serve the North Terminal, Concourse C, Concourse A, and the old Airfield Maintenance Building. Replace all hydrants and water valves that are encountered and install additional valves where needed. Abandon a section of water main located under Concourse A with a valve that is currently closed.
Priority:
Short
Need Origination:
M&O
Select One
5010
ALP/Master Plan
Community
FAA Initiatives
Inspection
Letter of Compliance
M&O
Other
Sponsor
State Equipment Fleet (SEF)
Justification:
The existing water mains provide water for firefighting protection for the Terminal and old Maintenance Building. The water mains located at the Terminal are estimated to have 10-15 years life remaining and the existing water mains at the old Airfield Maintenance Building are estimated to have 5-10 years life remaining. Trenchless improvements are proposed to extend the useful life of the existing water mains and prevent the need for replacement with open trenches in the future.
Notes:
ACIP Code: ST-TE-IM BIL AIG
Last Edit Date:
2/12/2024 09:30 AM
History Log
Jodi Gould
Need Created
11/29/2022 04:12 PM
Jodi Gould
In Project
11/29/2022 04:29 PM
Jodi Gould
Need Created
12/5/2022 12:56 PM
Removed from project.
Jodi Gould
In Project
12/5/2022 02:50 PM
Cristin Jones
Need Created
12/28/2022 01:59 PM
Removed from project.
Cristin Jones
In Project
12/28/2022 01:59 PM
Ian Rockmoore
Need Created
2/12/2024 09:28 AM
Removed from project.
Ian Rockmoore
In Project
2/12/2024 09:29 AM
Ian Rockmoore
Need Created
2/12/2024 09:29 AM
Removed from project.
Ian Rockmoore
In Project
2/12/2024 09:30 AM