Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date |
Acquire replacement water rescue rafts
|
Short
|
Letter of Compliance
|
M&O AIP
|
In Project
|
$36,392
| 3/17/2021 |
Construct SREB
|
Short
|
M&O
|
AIP
|
In Project
|
$12,512,500
| 11/15/2023 |
Cordova Airport ARFF Building Replacement
|
Mid
|
Other
|
AIP
|
In Project
|
$12,512,500
| 11/15/2023 |
Cordova Airport Perimeter Fence Installation
|
Mid
|
Other
|
AIP
|
In Project
|
$5,273,733
| 3/12/2019 |
Purchase New 3,000 gal. ARFF Truck
|
Short
|
State Equipment Fleet (SEF)
|
M&O AIP
|
In Project
|
$1,320,000
| 10/12/2022 |
Replace 37317 Cradle Broom
|
Short
|
State Equipment Fleet (SEF)
|
M&O AIP
|
In Project
|
$879,486
| 1/27/2022 |
Replace 37388 Rotary Plow with new Multi Carrier
|
Mid
|
M&O
|
AIP
|
In Project
|
$960,000
| 10/27/2023 |
Replace Damaged Culverts
|
Short
|
Inspection
|
M&O AIP
|
In Project
|
$597,024
| 9/1/2016 |
Runway 9/27 Rehabilitation
|
Short
|
Inspection
|
AIP
|
In Project
|
$30,900,000
| 3/11/2021 |
Runway Resurfacing
|
Mid
|
Inspection
|
AIP
|
In Project
|
$1,194,051
| 9/1/2016 |
Update Airport Master Plan Study
|
Short
|
Other
|
AIP
|
In Project
|
$654,044
| 1/8/2020 |
Cordova Airport Security Upgrades
|
N/A
|
Other
|
Local
|
Need Created
|
$3,074,682
| 6/16/2022 |
GA and Cargo aircraft parking
|
N/A
|
ALP/Master Plan
|
AIP
|
Need Created
|
$6,740,544
| 4/15/2022 |
Heliport pad, aviation support areas
|
N/A
|
ALP/Master Plan
|
AIP
|
Need Created
|
$265,077
| 4/15/2022 |
Install Continuously Operating Reference Stations (CORS)
|
Short
|
Sponsor
|
Stimulus
|
Need Created
|
$75,000
| 3/24/2022 |
Runway 9/27 Tree Removal
|
Short
|
Inspection
|
M&O AIP
|
Need Created
|
$132,538
| 4/15/2022 |
Sand Storage Repairs
|
Mid
|
Inspection
|
M&O AIP
|
Need Created
|
$198,808
| 4/15/2022 |
Taxiway B Resurfacing
|
Mid
|
Inspection
|
AIP
|
Need Created
|
$2,286,600
| 6/16/2022 |
Construct Tie-Downs
|
Long
|
Community
|
N/A
|
Need Created
|
| 4/14/2022 |
| | | | |
Total
| |