Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date | Last Verified Date |
Acquire replacement water rescue rafts
Acquire replacement water rescue rafts
|
Short
|
Letter of Compliance
|
AIP
|
In Project
|
$36,392
| 3/17/2021 | |
Construct SREB
Construct SREB
|
Short
|
M&O
|
AIP
|
In Project
|
$12,512,500
| 11/15/2023 | |
Cordova Airport ARFF Building Replacement
Cordova Airport ARFF Building Replacement
|
Mid
|
Other
|
AIP
|
In Project
|
$12,512,500
| 11/15/2023 | |
Cordova Airport Perimeter Fence Installation
Cordova Airport Perimeter Fence Installation
|
Mid
|
Other
|
AIP
|
In Project
|
$5,273,733
| 3/12/2019 | |
Purchase New 3,000 gal. ARFF Truck
Purchase New 3,000 gal. ARFF Truck
|
Short
|
State Equipment Fleet (SEF)
|
AIP
|
In Project
|
$1,320,000
| 10/12/2022 | |
Replace 37317 Cradle Broom
Replace 37317 Cradle Broom
|
Short
|
State Equipment Fleet (SEF)
|
AIP
|
In Project
|
$905,870
| 1/27/2022 | |
Replace 37388 Rotary Plow with new Multi Carrier
Replace 37388 Rotary Plow with new Multi Carrier
|
Mid
|
M&O
|
AIP
|
In Project
|
$960,000
| 10/27/2023 | |
Replace Damaged Culverts
Replace Damaged Culverts
|
Short
|
Inspection
|
AIP
|
In Project
|
$614,934
| 9/1/2016 | |
Runway 9/27 Rehabilitation
Runway 9/27 Rehabilitation
|
Short
|
Inspection
|
AIP
|
In Project
|
$30,900,000
| 3/11/2021 | |
Runway Resurfacing
Runway Resurfacing
|
Mid
|
Inspection
|
AIP
|
In Project
|
$1,229,872
| 9/1/2016 | |
Update Airport Master Plan Study
Update Airport Master Plan Study
|
Short
|
Other
|
AIP
|
In Project
|
$654,044
| 1/8/2020 | |
GA and Cargo aircraft parking
GA and Cargo aircraft parking
|
N/A
|
ALP/Master Plan
|
AIP
|
Need Created
|
$6,942,760
| 4/15/2022 | |
Heliport pad, aviation support areas
Heliport pad, aviation support areas
|
N/A
|
ALP/Master Plan
|
AIP
|
Need Created
|
$273,029
| 4/15/2022 | |
Install Continuously Operating Reference Stations (CORS)
Install Continuously Operating Reference Stations (CORS)
|
Short
|
Sponsor
|
Stimulus
|
Need Created
|
$75,000
| 3/24/2022 | |
Runway 9/27 Tree Removal
Runway 9/27 Tree Removal
|
Short
|
Inspection
|
AIP
|
Need Created
|
$136,514
| 4/15/2022 | |
Sand Storage Repairs
Sand Storage Repairs
|
Mid
|
Inspection
|
AIP
|
Need Created
|
$204,772
| 4/15/2022 | |
Taxiway B Resurfacing
Taxiway B Resurfacing
|
Mid
|
Inspection
|
AIP
|
Need Created
|
$2,286,600
| 6/16/2022 | |
Construct Tie-Downs
Construct Tie-Downs
|
Long
|
Community
|
N/A
|
Need Created
|
| 4/14/2022 | |
| | | | |
Total
| | |