Alaska Department of Transportation and Public Facilities
ALASKA AVIATION DATABASE
a component of the
Alaska Aviation System Plan

KODIAK: AIP Grants

Base Information
Owner: ALASKA DOT&PF SOUTHCOAST REGION
NPIAS: 02-0158
Airport Use: Public
Type: Airport
FAA Associated City: KODIAK
DOT&PF Region: Southcoast
DOT Owned: True
Facility Status: Active
Filter +/-
Federal Fiscal Year (FFY):
Purpose:    
Purpose Definition
CA Capacity
EN Environment
OT Other
PL Planning
RC Reconstruction
RE Rehabilitate
SA Safety/Security
SB State Block Grant Program
SE Security Enhancements
SP Statutory Emphasis Programs
ST Standards
Component:    
Component Definition
RW Runway Projects
TW Taxiway Projects
AP Apron Projects
TE Terminal Projects
BD Building Projects (other than terminals)
GT Ground Transportation Projects
EQ Equipment, Security, and Fencing
OT Other Projects
LA Land Acquisition (other than noise land)
NA New Airport Projects
PL Planning Projects
SB Seaplane Base Projects
HE Heliport/Helipad Projects
VT Vertiport Projects
HO Noise Projects (other than planning)
PB Noise Mitigation Measures for Public Buildings
Type:    
Type Definition
60 Noise Mitigation Measures for Residences outside 65 DNL
65 Noise Mitigation Measures for Residences within 65 - 69 DNL
70 Noise Mitigation Measures for Residences within 70 - 74 DNL
75 Noise Mitigation Measures for Residences within 75 DNL
AC Access
AQ Acquire Existing Airport
CO Construct
DI Deicing
DV Development
ES Environment Sustainable
EX Extend
FF Fuel Farm
FR Groove Runway
IM Improve
Type Definition
IN Install Instruments
LI Lighting
MA Master Planning
ME Metropolitan System Plan
MS Miscellaneous
MT Environmental Mitigation
NO Noise
OB Obstructions
PA Parking
PM People Mover
PR On-Airport Energy Production
RF Rescue & Fire Fighting
RL Rail
SE Security Enhancements
Type Definition
SF Safety Area
SG Guidance Signs
SN Snow Removal
SR Sensors
ST State System Plan
SV Service Road
SZ Acquire land/easement for approaches
VI Vertical/Visual Guidance System
VT Conduct Vertiport Plan
WH Wildlife Hazard Assessments
WR Construct Wash Rack
WX Install Weather Reporting Equipment
ZE Zero Emissions Vehicle/Infrastructure
Grant Agreement Date:
to
Status:
 
 
Grant Summary Statistics
Total Grants: 51
Total Number of Grant Work Codes: 79 Total Grants: $167,294,869.00
Total Number of Open Grant Work Codes: 17 Total Open Grants: $40,527,504.00
Total Number of Closed Grant Work Codes: 62 Total Closed Grants: $126,767,365.00
 
AIP Grant Listing
The following listing displays all grants since the initiation of the Airport Improvement Program in 1982, most recent to oldest, with the exception of the current federal fiscal year. Grant Agreement Date refers to the date the grant was initiated, Closeout Submitted to FAA notes the date DOT&PF staff submitted a closeout package for review, and Grant Close Date is the official grant closure date, as reported by the FAA. Total cost below includes all AIP funding types (entitlement, discretionary, etc.).
Additional details are exportable into Excel or by going to Reports >> AIP Grants.
FFY    Grant Number    

Each Airport Improvement Program (AIP) grant has a distinct number from the beginning of the program in 1982 to present day. All grants are for the planning and development of public-use airports included in the National Plan of Integrated Airport Systems (NPIAS).

3-02-0000-024-2018 FAA Region (Alaskan)

3-02-0000-024-2018 Airport NPIAS number, assigned to all NPIAS airports starting with 0001 for Adak. 0200 is used for various multi-airport grants (such as pavement marking, various surface maintenance, etc.) and 0000 is used for State System Grants such as the statewide system planning grant.

3-02-0000-024-2018 Grant Sequence Number (this is the 24th grant at this facility)

3-02-0000-024-2018 Federal Fiscal Year Grant Awarded

Work Code    

FAA defines project work codes as a 6-character alpha identifier consisting of three 2-character elements that express purpose, component and type, represents specific airport development and is used in the national priority system equation to produce a numerical rating. Each 2-character alpha identifier may be assigned a value ranging from 0 to 10.

(1) The purpose (P) identifier signifies the underlying objective of an airport development project (e.g., reconstruct, planning, safety). There are approximately 13 purpose identifiers.

(2) The component (C) identifier signifies the physical component (e.g., runway, airfield, planning), for which the development is intended. There are approximately 31 component identifiers.

(3) The type (T) identifier signifies the actual work being done (e.g., expand/extend, construct, update). There are approximately 61 type identifiers.

More information is available in the FAA Order 5090.5, Formulation of the NPIAS and ACIP.

Project DescriptionGrant Agreement DateCloseout Submitted to FAAGrant Close DateTotal
2024 3-02-0158-024-2024 RC AP IM Reconstruct Apron 8/6/2024 $20,135,419
2024 3-02-0158-024-2024 ST AP EX Expand Apron 8/6/2024 $629,221
2024 3-02-0158-024-2024 ST AF DR Improve Airport Drainage/Erosion Control 8/6/2024 $2,696,660
2024 3-02-0158-026-2024 RC TW IM Reconstruct Taxiway 8/19/2024 $824,069
2024 3-02-0158-026-2024 RC TW LI Reconstruct Taxiway Lighting 8/19/2024 $289,764
2024 3-02-0158-027-2024 RS RW IM Reseal/Resurface Runway Pavement 8/6/2024 $211,193
2024 3-02-0158-027-2024 RS TW IM Reseal Taxiway Pavement 8/6/2024 $28,125
2024 3-02-0158-028-2024 RC FE SE Reconstruct Perimeter Security Fencing 9/10/2024 $3,743,356
2024 3-02-0158-028-2024 SE EQ AQ Acquire Security Equipment 9/10/2024 $1,302,310
2022 3-02-0158-023-2022 CV RG GN General ARPA 12/14/2021 $1,572,977
2021 3-02-0158-021-2021 CV CR GN CRRSA Act Funds 4/26/2021 $1,180,034
2021 3-02-0158-022-2021 RC EQ SE Reconstruct Perimeter Fencing required by 49 CFR 1542 8/11/2021 $7,313,105
2019 3-02-0200-125-2019 RE RW IM [Various Grant] Rehabilitate Runway 01/19 Various SPM (Kodiak): Rehabilitate Marking for Runways 8/26 and 1/19 and, incidentally, Taxiways B, C, D, E, and F, and Aprons A and B 9/27/2019 $51,575
2019 3-02-0200-125-2019 RE RW IM [Various Grant] Rehabilitate Runway 08/26 Various SPM (Kodiak): Rehabilitate Marking for Runways 8/26 and 1/19 and, incidentally, Taxiways B, C, D, E, and F, and Aprons A and B. 9/27/2019 $77,361
2019 3-02-0200-124-2019 ST OT OB [Various Grant] Remove Obstructions [Non-Hazard] Various Obstruction Removal (Kodiak): Remove tree obstructions in RWY 8 20:1 Approach Surface. 9/23/2019 $268,617
2018 3-02-0200-122-2018 RE RW IM [Various Grant] Rehabilitate Runway 08/26 Various SPM - Kodiak (Markings and Crack Seal on RWY 08/26, and, incidentally, TWY's and Aprons) 9/18/2018 $101,859
2018 3-02-0200-122-2018 RE RW IM [Various Grant] Rehabilitate Runway 01/19 Various SPM - Kodiak (Marking and Crack Seal on RWY 1/19, and, incidentally, TWY's and Aprons) 9/18/2018 $101,859
2017 3-02-0200-118-2017 RE RW IM [Various Grant] Rehabilitate Runway 01/19 Various Surface Preservation Maintenance (Kodiak) - Re- Marking Runway 1/19 and Runway 8/26 (and incidentally Taxiways B, C, D, E, and F, and Aprons A and B) 9/21/2017 2/11/2022 2/25/2022 $41,201
2017 3-02-0200-113-2017 OT EQ MS [Various Grant] Acquire Interactive Training System Various 139 Airports - Acquire Interactive Training System 9/21/2017 7/15/2021 11/30/2021 $11,443
2017 3-02-0200-118-2017 RE RW IM [Various Grant] Rehabilitate Runway 08/26 Various Surface Preservation Maintenance (Kodiak) - Re- Marking Runway 1/19 and Runway 8/26 (and incidentally Taxiways B, C, D, E, and F, and Aprons A and B) 9/21/2017 2/11/2022 2/25/2022 $61,802
2016 3-02-0158-020-2016 SA EQ RF Acquire Aircraft Rescue & Fire Fighting Vehicle Acquire ARFF Vehicle (1,500-Gallon, Kodiak) 9/19/2016 12/1/2020 1/3/2022 $576,130
2016 3-02-0200-109-2016 RE RW IM [Various Grant] Rehabilitate Runway 01/19 Various Surface Preservation Maintenance (Kodiak) [This grant will fund Remarking on Runway 1/19 (     linear feet), Taxiway (     linear feet) and Apron (     square yards) at the Kodiak Airport.] 9/19/2016 12/1/2020 11/22/2021 $103,003
2015 3-02-0200-101-2015 ST EQ SN [Various Grant] Acquire Snow Removal Equipment Acquire Various SRE (Kodiak Loader) 9/21/2015 12/7/2020 11/18/2021 $326,279
2015 3-02-0200-104-2015 RE RW IM [Various Grant] Rehabilitate Runway 18/36 Accomplish Various Airport Surface Preservation Maintenance (Kodiak Crack Sealing and Marking) 9/21/2015 7/18/2022 7/18/2022 $241,500
2015 3-02-0158-019-2015 ST OT IM Improve Airport Drainage 4/20/2015 1/19/2021 9/2/2021 $2,584,000
2014 3-02-0158-017-2014 SA RW SF Extend Runway Safety Area 07/25 Construction Phase 2 6/16/2014 12/11/2020 12/21/2021 $22,250,000
2014 3-02-0158-018-2014 SA RW SF Extend Runway Safety Area 07/25 Phase 3 9/23/2014 12/15/2020 12/21/2021 $4,850,000
2014 3-02-0158-017-2014 SA RW SF Extend Runway Safety Area 18/36 Construction, Phase 2 6/16/2014 12/11/2020 12/21/2021 $24,250,000
2014 3-02-0158-018-2014 SA RW SF Extend Runway Safety Area 18/36 Phase 3 9/23/2014 12/15/2020 12/21/2021 $5,139,000
2014 3-02-0200-095-2014 SA OT OB [Various Grant] Remove Obstructions Various Obstruction Removal (+08J) 9/22/2014 6/24/2020 11/29/2021 $264,000
2014 3-02-0200-098-2014 RE RW IM [Various Grant] Rehabilitate Runway 18/36 (+08J) Various Surface Preservation Maintenance: Kodiak - Crack Seal, Pavement Markings 9/19/2014 11/30/2021 2/16/2022 $341,500
2013 3-02-0200-093-2013 RE RW IM [Various Grant] Rehabilitate Runway 07/25 Surface Preservation Maintenance (Kodiak) 9/18/2013 7/15/2020 $404,300
2013 3-02-0200-094-2013 ST EQ SN [Various Grant] Acquire Snow Removal Equipment Acquire SRE (Tow Plow) 9/19/2013 3/12/2018 $102,267
2013 3-02-0158-016-2013 SA RW SF Extend Runway Safety Area 18/36 Construction, phase 1 9/24/2013 7/18/2018 $7,000,000
2013 3-02-0158-016-2013 SA RW SF Extend Runway Safety Area 07/25 Construction Phase 1 9/24/2013 7/18/2018 $6,000,000
2012 3-02-0158-015-2012 EN PL MA Conduct Environmental Study EIS phase 4 9/10/2012 3/24/2015 $1,025,558
2012 3-02-0200-086-2012 ST EQ SN [Various Grant] Acquire Snow Removal Equipment Acquire SRE (Alaska Region): Kodiak (Towed Sweeper, Loader with Attachments) 9/11/2012 7/19/2017 $643,488
2012 3-02-0200-087-2012 RE RW IM [Various Grant] Rehabilitate Runway 18/36 Various Surface Preservation Maintenance (Kodiak) 9/19/2012 1/9/2019 $10,000
2011 3-02-0200-079-2011 RE RW IM [Various Grant] Rehabilitate Runway 07/25 Various Surface Preservation 9/16/2011 6/6/2017 $113,880
2011 3-02-0158-014-2011 RE TW IM Rehabilitate Taxiway Rehab taxiway B 9/16/2011 7/5/2017 $579,055
2011 3-02-0158-014-2011 RE RW IM Rehabilitate Runway 07/25 Reconstruct Runway, phase 1(LOC) 9/16/2011 7/5/2017 $14,984,080
2011 3-02-0158-013-2011 RE RW IM Rehabilitate Runway 18/36 Rehabilitate Runway 6/13/2011 7/5/2017 $10,083,780
2011 3-02-0158-013-2011 RE RW LI Rehabilitate Runway Lighting 18/36 Edge lighting, regulators, regulator bldg 6/13/2011 7/5/2017 $2,000,000
2010 3-02-0158-012-2010 ST BD SN Construct Sand and Chemical Storage Building Construct Chemical Storage Building (part C) 6/22/2010 3/1/2017 $2,796,971
2010 3-02-0200-073-2010 RE RW IM [Various Grant] Rehabilitate Runway 07/25 Kodiak Various Surface Maintenance 3/12/2010 12/9/2015 $100,000
2010 3-02-0200-075-2010 ST EQ SN [Various Grant] Acquire Snow Removal Equipment Acquire SRE (Central Region): Kodiak (Grader with Attachments) 9/3/2010 1/20/2015 $324,926
2009 3-02-0200-072-2009 SA EQ RF [Various Grant] Acquire Safety and/or Security Equipment Acquire Water Rescue Plan Equipment 9/24/2009 11/12/2014 $100,000
2009 3-02-0200-069-2009 RE RW IM [Various Grant] Rehabilitate Runway 07/25 (Various Surface Maintenance) 8/20/2009 12/19/2014 $1,439,439
2009 3-02-0158-011-2009 SA RW SF Extend Runway Safety Area 07/25 EIS Phase 3 2/25/2009 3/24/2015 $817,198
2009 3-02-0158-011-2009 SA RW SF Extend Runway Safety Area 18/36 (EIS Phase 3) 2/25/2009 3/24/2015 $750,000
2008 3-02-0200-065-2008 ST EQ SN [Various Grant] Acquire Snow Removal Equipment Acquire SRE: ADQ--D-6 Dozer w/ attachments, & Self-Propelled Blower 6/16/2008 2/5/2014 $750,000
2008 3-02-0200-066-2008 RE RW IM [Various Grant] Rehabilitate Runway 07/25 (Maintenance) 6/19/2008 6/10/2014 $100,000
2007 3-02-0200-060-2007 RE RW IM [Various Grant] Rehabilitate Runway 07/25 (Maintenance) 5/31/2007 8/6/2013 $109,600
2007 3-02-0158-010-2007 SA RW SF Extend Runway Safety Area 18/36 (EIS Phase 2) 8/9/2007 3/24/2015 $1,743,000
2007 3-02-0158-010-2007 SA RW SF Extend Runway Safety Area 07/25 EIS Phase 2 8/9/2007 3/24/2015 $1,743,000
2006 3-02-0200-056-2006 RE RW IM [Various Grant] Rehabilitate Runway 07/25 (Maintenance) 6/30/2006 2/27/2012 $207,739
2005 3-02-0200-052-2005 RE RW IM [Various Grant] Rehabilitate Runway 07/25 (Maintenance) 8/30/2005 6/9/2010 $40,000
2005 3-02-0200-052-2005 RE RW IM [Various Grant] Rehabilitate Runway 18/36 (Maintenance) 8/30/2005 6/9/2010 $40,000
2005 3-02-0200-052-2005 RE RW IM [Various Grant] Rehabilitate Runway 11/29 (Maintenance) 8/30/2005 6/9/2010 $40,000
2005 3-02-0158-009-2005 SA RW SF Extend Runway Safety Area 07/25 (EIS) 8/15/2005 4/13/2010 $500,000
2005 3-02-0158-009-2005 SA RW SF Extend Runway Safety Area 18/36 (EIS) 8/15/2005 4/13/2010 $500,000
2000 3-02-0158-008-2000 RE AP IM Rehabilitate Apron 9/7/2000 8/26/2004 $1,311,062
2000 3-02-0158-008-2000 RE RW IM Rehabilitate Runway 9/7/2000 8/26/2004 $2,105,188
2000 3-02-0158-008-2000 RE TW IM Rehabilitate Taxiway 9/7/2000 8/26/2004 $1,185,656
1999 3-02-0158-007-1999 PL PL MA Conduct Airport Master Plan Study 3/19/1999 11/17/2006 $335,929
1999 3-02-0158-006-1999 ST BD SN Improve Snow Removal Equipment Building 3/19/1999 9/11/2002 $1,648,754
1999 3-02-0158-006-1999 SA OT OB Remove Obstructions 18/36 3/19/1999 9/11/2002 $500,000
1993 3-02-0158-005-1993 SA EQ SE Acquire Security Equipment 9/14/1993 9/25/1997 $882,292
1989 3-02-0158-004-1989 ST EQ MS Acquire Aircraft Rescue & Fire Fighting Safety Equipment 6/28/1989 2/25/1991 $127,831
1989 3-02-0158-004-1989 SA OT OB Remove Obstructions 6/28/1989 2/25/1991 $14,392
1988 3-02-0158-003-1988 RE RW IM Rehabilitate Runway 7/25 8/17/1988 4/2/1991 $1,592,371
1987 3-02-0158-002-1987 ST TW IM Extend Taxiway 0/28 6/29/1987 9/27/1989 $90,049
1987 3-02-0158-002-1987 ST AP LI Install Apron Lighting 6/29/1987 9/27/1989 $82,260
1987 3-02-0158-002-1987 ST RW LI Install Runway Lighting 6/29/1987 9/27/1989 $18,110
1987 3-02-0158-002-1987 ST RW LI Install Runway Lighting 6/29/1987 9/27/1989 $276,467
1987 3-02-0158-002-1987 SA RW LI Install Runway Lighting 6/29/1987 9/27/1989 $7,043
1987 3-02-0158-002-1987 SA RW LI Install Runway Lighting 10/28 6/29/1987 9/27/1989 $168,207
1987 3-02-0158-002-1987 SA RW LI Install Runway Lighting 7/25 6/29/1987 9/27/1989 $65,500
1986 3-02-0158-001-1986 SA EQ RF Acquire Aircraft Rescue & Fire Fighting Vehicle 6/11/1986 2/5/1991 $268,115