Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date |
Acquire New Grader
|
Mid
|
M&O
|
AIP
|
In Project
|
$398,437
| 2/2/2023 |
Cone and Marker Repair / Replacement
|
ASAP
|
Inspection
|
AIP
|
In Project
|
$0
| 3/1/2020 |
Construct Tie-Downs
|
Long
|
Community
|
AIP
|
In Project
|
$0
| 1/15/2016 |
Dust Control
|
Short
|
Other
|
AIP
|
In Project
|
$359,407
| 3/1/2020 |
Rehab Threshold Markings
|
N/A
|
Inspection
|
AIP
|
In Project
|
$5,251
| 3/1/2020 |
Rehabilitate Apron
|
Short
|
Other
|
AIP
|
In Project
|
$725,655
| 2/26/2020 |
Rehabilitate Runway
|
Short
|
Other
|
AIP
|
In Project
|
$5,721,433
| 2/26/2020 |
Rehabilitate Runway 16/34 Lighting
|
ASAP
|
Other
|
AIP
|
In Project
|
$839,628
| 3/1/2020 |
Rehabilitate Taxiway
|
Short
|
Other
|
AIP
|
In Project
|
$276,894
| 2/26/2020 |
Repair Airport Signs
|
ASAP
|
Other
|
AIP
|
In Project
|
$0
| 3/1/2020 |
Replace Secondary Wind Cones and Poles
|
Short
|
Inspection
|
AIP
|
In Project
|
$11,938
| 3/1/2020 |
Replace Taxiway Lighting
|
Short
|
Other
|
AIP
|
In Project
|
$113,516
| 2/26/2020 |
Install ASOS or AWOS
|
Long
|
Community
|
AIP
|
Need Created
|
$2,121,800
| 11/23/2022 |
Construct Passenger Shelter
|
Long
|
Community
|
N/A
|
Need Created
|
| 11/23/2022 |
Construct Toilet Facilities
|
Long
|
Community
|
N/A
|
Need Created
|
| 11/23/2022 |
| | | | |