Owner:
|
ALASKA DOT&PF NORTHERN REGION
|
NPIAS:
|
02-0262
|
Airport Use:
|
Public
|
Type:
|
Airport
|
FAA Associated City:
|
NUNAM IQUA
|
DOT&PF Region:
|
Northern
|
DOT Owned:
|
True
|
Facility Status:
|
Active
|
|
ASAP Needs Total:
|
|
|
Short Term Needs Total:
|
|
Mid Term Needs Total:
|
|
|
Long Term Needs Total:
|
|
All Needs Total:
|
|
|
Needs in Project Total:
|
|
Number of Needs:
|
|
|
Number of Needs in Project:
|
|
Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date |
Acquire Loader (Replace #35036)
|
Mid
|
M&O
|
AIP
|
In Project
|
$450,000
| 10/27/2023 |
Acquire New Dozer
|
Mid
|
M&O
|
AIP
|
In Project
|
$407,812
| 2/3/2023 |
Acquire New Grader
|
Mid
|
M&O
|
AIP
|
In Project
|
$431,250
| 2/3/2023 |
Construct Access Road
|
|
Other
|
AIP
|
In Project
|
$4,044,000
| 10/17/2023 |
Construct Apron
|
|
Inspection
|
AIP
|
In Project
|
$2,000,000
| 10/17/2023 |
Construct Snow Removal Equipment Building
|
Long
|
Inspection
|
AIP
|
In Project
|
$2,750,000
| 10/17/2023 |
Construct Taxiway
|
|
Inspection
|
AIP
|
In Project
|
$1,750,000
| 9/23/2022 |
Extend / Improve Runway Safety Area
|
Mid
|
Community
|
AIP
|
In Project
|
$4,250,000
| 10/17/2023 |
Improve Airport Drainage
|
|
Inspection
|
AIP
|
In Project
|
$200,000
| 9/23/2022 |
Install Miscellaneous NAVAIDS
|
Long
|
Community
|
AIP
|
In Project
|
$325,000
| 10/17/2023 |
Minor Gravel Resurfacing and Dust Palliative
|
Short
|
Inspection
|
M&O AIP
|
In Project
|
$358,414
| 4/22/2021 |
Regrade, recover D-1 and re-establish crown on runway
|
Short
|
Inspection
|
M&O AIP
|
In Project
|
$0
| 4/22/2021 |
Rehabilitate Runway
|
Mid
|
M&O
|
AIP
|
In Project
|
$11,000,000
| 9/25/2023 |
Rehabilitate Runway Lighting
|
|
Inspection
|
AIP
|
In Project
|
$1,500,000
| 10/17/2023 |
Widen Runway 2/20
|
Short
|
Other
|
AIP
|
In Project
|
$2,000,000
| 10/17/2023 |
Access Road and Causeway Construction
|
Long
|
Other
|
N/A
|
Need Created
|
$3,689,619
| 9/26/2022 |
Reconstruct Runway 2/20
|
Long
|
Community
|
AIP
|
Need Created
|
$8,000,000
| 9/23/2022 |
Construct Passenger Shelter
|
Long
|
Community
|
N/A
|
Need Created
|
| 2/3/2023 |
Construct Toilet Facilities
|
Long
|
Community
|
N/A
|
Need Created
|
| 2/3/2023 |
| | | | |
Total
| |
|