Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date |
Acquire New Grader
|
Mid
|
M&O
|
AIP
|
In Project
|
$431,250
| 2/3/2023 |
Apply Dust Palliative
|
Short
|
Inspection
|
M&O AIP
|
In Project
|
$30,596
| 4/22/2021 |
Minor Gravel Resurfacing
|
Short
|
Other
|
M&O AIP
|
In Project
|
$309,000
| 4/22/2021 |
Minor Gravel Resurfacing & Dust Palliative (2026)
|
Mid
|
M&O
|
M&O AIP
|
In Project
|
$400,000
| 3/13/2023 |
Mountain Village SRE Building Replacement
|
Mid
|
Other
|
AIP
|
In Project
|
$2,111,191
| 3/18/2019 |
Purchase Loader
|
Mid
|
M&O
|
M&O AIP
|
In Project
|
$434,969
| 10/13/2022 |
Reconstruct Runway 2/20
|
Short
|
Inspection
|
AIP
|
In Project
|
$1,250,000
| 9/23/2022 |
Reconstruct Runway Lighting
|
ASAP
|
Inspection
|
AIP
|
In Project
|
$800,000
| 9/23/2022 |
Reconstruct Taxiway Lighting
|
ASAP
|
Inspection
|
AIP
|
In Project
|
$400,000
| 9/23/2022 |
Replace Miscellaneous NAVAID
|
Short
|
Inspection
|
AIP
|
In Project
|
$800,000
| 9/23/2022 |
Resurface Access Road
|
Mid
|
Inspection
|
AIP
|
In Project
|
$200,000
| 9/23/2022 |
Resurface Apron
|
Short
|
Inspection
|
AIP
|
In Project
|
$1,500,000
| 9/23/2022 |
Resurface Runway 2/20
|
Short
|
Inspection
|
AIP
|
In Project
|
$11,000,000
| 9/23/2022 |
Resurface Taxiways
|
Short
|
Inspection
|
AIP
|
In Project
|
$2,500,000
| 9/23/2022 |
Construct Passenger Shelter
|
Long
|
Community
|
N/A
|
Need Created
|
| 2/3/2023 |
Construct Toilet Facilities
|
Long
|
Community
|
N/A
|
Need Created
|
| 2/3/2023 |
| | | | |
Total
| |