Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date |
Acquire New Grader
|
Short
|
M&O
|
AIP
|
In Project
|
$431,250
| 1/20/2023 |
Elim Dozer
|
Short
|
State Equipment Fleet (SEF)
|
M&O AIP
|
In Project
|
$393,460
| 3/17/2021 |
Replace Segmented Circle
|
Short
|
Inspection
|
M&O AIP
|
In Project
|
$164,439
| 4/25/2022 |
Resurface and Apply Dust Palliative to RWY, TW, Apron, and Airport Access Road
|
Mid
|
M&O
|
M&O AIP
|
In Project
|
$375,000
| 2/3/2023 |
Realign Access Road
|
Long
|
ALP/Master Plan
|
AIP
|
Need Created
|
$8,609,114
| 7/7/2022 |
Upgrade Existing SREB
|
Short
|
Other
|
AIP
|
Need Created
|
$503,393
| 11/9/2017 |
Construct Passenger Shelter
|
Long
|
Community
|
N/A
|
Need Created
|
| 7/7/2022 |
Construct Tie-Downs
|
Long
|
Community
|
N/A
|
Need Created
|
| 7/7/2022 |
Construct Toilet Facilities
|
Long
|
Community
|
N/A
|
Need Created
|
| 7/7/2022 |
| | | | |
Total
| |