KING SALMON: Airport Needs List

Owner: ALASKA DOT&PF SOUTHCOAST REGION
NPIAS: 02-0148
Airport Use: Public
Type: Airport
FAA Associated City: KING SALMON
DOT&PF Region: Southcoast
DOT Owned: True
Facility Status: Active
Filter +/-
Needs Funding Source:
Status:
Need Category:
M&O Activity:
 
ASAP Needs Total:   Short Term Needs Total:
Mid Term Needs Total: Long Term Needs Total:
All Needs Total: Needs in Project Total:
Number of Needs: Number of Needs in Project:
 
NeedsPriorityNeed OriginationFunding SourceStatusEstimated CostLast Edit DateLast Verified Date
Procure AFFF Testing Equipment
Procure AFFF Testing Equipment
ASAP FAA Initiatives AIP Constructed/Purchased $24,000 5/6/2026 
Apron Lighting
Apron Lighting
Short Other AIP In Project $162,596 10/2/2023 
Apron Markings
Apron Markings
ASAP Inspection AIP In Project $0 8/23/2019 
Construct 4-Bay SRE Building
Construct 4-Bay SRE Building
Short Inspection AIP In Project $5,871,474 2/14/2019 
Conx to Generator
Conx to Generator
Short M&O AIP In Project $308,371 10/2/2023 
Distance To Go Signs
Distance To Go Signs
Short M&O AIP In Project $245,295 10/2/2023 
Install 5 Auto-Gate Proxy Readers
Install 5 Auto-Gate Proxy Readers
Short Inspection AIP In Project $65,236 2/9/2021 
Lighting RWY 12-30 Reconstruct
Lighting RWY 12-30 Reconstruct
Short M&O AIP In Project $856,572 10/2/2023 
Rehab lighting TWYs A, B, C, D, E, and G
Rehab lighting TWYs A, B, C, D, E, and G
Short Other AIP In Project $601,604 10/2/2023 
Rehab Pavements Terminal & GA Aprons
Rehab Pavements Terminal & GA Aprons
Short Inspection AIP In Project $17,924,095 10/2/2023 
Rehab RWY 18-36 Lighting
Rehab RWY 18-36 Lighting
ASAP Other AIP In Project $255,458 10/2/2023 
Rehab TWY Pavements
Rehab TWY Pavements
Short Inspection AIP In Project $7,632,563 10/2/2023 
Rehabilitate GA Apron and Taxiway G
Rehabilitate GA Apron and Taxiway G
N/A Other AIP In Project $0 6/19/2015 
Rehabilitate Runway 18/36 and Runway 18 Overrun
Rehabilitate Runway 18/36 and Runway 18 Overrun
ASAP FAA Initiatives AIP In Project $28,137,720 1/29/2022 
Rehabilitate Taxiways
Rehabilitate Taxiways
Short Inspection N/A In Project $0 1/29/2022 
Rehabilitate TWY C
Rehabilitate TWY C
Short Inspection AIP In Project $0 10/8/2021 
Remove leadin Twy
Remove leadin Twy
ASAP Letter of Compliance AIP In Project $6,556,362 10/11/2018 
Remove Taxiway P
Remove Taxiway P
Short Inspection AIP In Project $0 6/19/2015 
Replace edge lighting
Replace edge lighting
N/A Other N/A In Project $0 8/23/2019 
Replace windsock
Replace windsock
Short Letter of Compliance AIP In Project $93,446 10/2/2023 
Runway lights
Runway lights
Short Inspection AIP In Project $0 1/29/2022 
Runway turnaround
Runway turnaround
Short Other AIP In Project $0 8/23/2019 
Upgrade Airport Access Controls
Upgrade Airport Access Controls
Mid Other AIP In Project $2,121,800 2/9/2021 
Apron: RE AP IM: Rehabilitate Apron
Hardstand
Short M&O AIP Need Created $3,000,000 11/21/2024 
Crack Seal
Crack Seal
Short M&O AIP Need Created $187,500 1/23/2023 
Install Continuously Operating Reference Stations (CORS)
Install Continuously Operating Reference Stations (CORS)
Short Sponsor Stimulus Need Created $75,000 3/24/2022 
Install REIL and PAPI for Runway 18/36
Install REIL and PAPI for Runway 18/36
Long Inspection AIP Need Created $461,458 4/19/2022 
Construct Tie-Downs
Construct Tie-Downs
Long Community N/A Need Created 4/19/2022 
Public Restrooms
Public Restrooms
Short Community N/A Need Created 8/7/2023 
Acquire replacement water rescue rafts
Acquire replacement water rescue rafts
Short Letter of Compliance AIP Obligated Need $36,392 3/17/2021 
Master Plan Update
Master Plan Update
Short Inspection AIP Obligated Need $983,454 8/2/2023 
Equipment: RE EQ SN: Rehabilitate Snow Removal Equipment
Acquire New Loader
Short M&O AIP Programmed Need $475,000 11/25/2024 
Runway Projects: RC RW IM : Reconstruct Runway
Painted Markings 2029
Long M&O AIP Programmed Need $140,000 1/20/2026 
Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
Paint Markings on RW 12/30, TW B and West Apron
Short M&O AIP Programmed Need $288,025 9/17/2025 
Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
Pavement Markings (2027)
Mid M&O AIP Programmed Need $140,000 9/17/2025 
      Total   
Needs List Process Flow