Alaska Department of Transportation and Public Facilities
ALASKA AVIATION DATABASE
a component of the
Alaska Aviation System Plan

Need Overview

Need Name: Runway Pavement Rehab
Type:
Funding Source:
Category:
Sub Category:
Estimated Cost: $7,926,892
Description: Mill and Pave the runway pavement
Priority: Short
Need Origination: Inspection
Justification: The 2023 PCI report shows the runway will need rehabilitation by the year 2027. By the time the airport is repaved, the pavement will be 18-22 years old.
Notes:
Last Edit Date: 2/16/2024 10:04 AM
History Log
Paul Khera
Need Created
12/18/2023 03:51 PM
Paul Khera
In Project
12/20/2023 11:40 AM
Paul Khera
Need Created
2/16/2024 10:03 AM
Removed from project.
Paul Khera
In Project
2/16/2024 10:32 AM

Inspection Photos