Need Name:
Rehabilitate Taxiway Pavement
Type:
AIP/M&O AIP
Community/Economic Development
Funding Source:
Select One
State GF
AIP
M&O AIP
M&O Operating
Stimulus
Local
Bond
N/A
Category:
Select One
APRON
BUILDING
EQUIPMENT
FENCING
GROUND TRANSPORTATION
HELIPAD
LEASING
NEW AIRPORT
OTHER
PLANNING
RUNWAY
SEAPLANE BASE
TAXIWAY
Sub Category:
Select One
Construct Taxiway
Demolish Taxiway
Extend Taxiway
Install Taxiway Lighting
Install Taxiway Sensors
Rehabilitate Taxiway
Rehabilitate Taxiway Lighting
Relocate Taxiway
Strengthen Taxiway
Widen Taxiway
Estimated Cost:
$522,240
Description:
Mill and pave the taxiway.
Priority:
Short
Need Origination:
Sponsor
Select One
5010
ALP/Master Plan
Community
FAA Initiatives
Inspection
Letter of Compliance
M&O
Other
Sponsor
State Equipment Fleet (SEF)
Justification:
The taxiway will need a mill and pave around the 2028-2030 time period when the pavement is well past it's useful life. Because the airport serves jet traffic, we cannot wait until the 2026 PCI Report. We have to address this now.
Notes:
RE TW IM
Last Edit Date:
2/27/2024 03:36 PM
History Log
Paul Khera
Need Created
11/13/2023 04:05 PM
Paul Khera
In Project
11/14/2023 11:11 AM
Paul Khera
Need Created
2/27/2024 03:19 PM
Removed from project.
Paul Khera
In Project
2/27/2024 03:43 PM