Need Overview
Need Name:
Misc. Navaids
Type:
AIP
Community/Economic Development
M&O Operating
Funding Source:
Select One
State GF
AIP
M&O Operating
Stimulus
N/A
Category:
Select One
Access Road
Airfield
Airport Master Planning
Airside
Apron
ARPA
Building
Building and Equipment (Control Tower)
CARES Act
CRRSA Act
Equipment
Financing
Ground Transportation
Helipad/Heliport
Homes
Land
Landside
Metro Area Planning
Multi Modal
New Airport
Noise
Other
People Mover
Planning
Privatization Planning
Public Building
Rail
Revenue Producing
Runway
Sealane
Seaplane Base
Service/Perimeter Road
State Block Grant Program
State/Regional Planning
Taxilane
Taxiway
Terminal
Sub Category:
Select One
Estimated Cost:
$2,257,000
Description:
This project proposes to resurface the gravel runway, taxiway, apron, and access road. The runway surface will be widened to achieve crosswind coverage. Improvements include replacement of airfield lighting, markings, signs, and navigational aids. There will be erosion protection and obstruction removal.
Priority:
Short
Need Origination:
Sponsor
Select One
5010
ALP/Master Plan
Community
FAA Initiatives
Inspection
Letter of Compliance
M&O
Other
Sponsor
State Equipment Fleet (SEF)
Justification:
The airport's operational surfaces and access road are in fair to poor condition. Differential settling, irregular surfaces, and dips cause issues for pilots using the operational surfaces and for residents accessing the airport road. The runway and taxiway lighting systems are beyond their useful life and need to be replaced to maintain reliability for operations during nighttime and inclement weather. The current wind coverage is below FAA recommendations and widening will achieve the 95% goal.
Notes:
CIPDS associated with 4/7/2022 APEB and submitted to FAA on 3/18/2022
Last Edit Date:
3/9/2022 03:00 PM
History Log
Jessica Wuttke-Campoamor
Need Created
3/9/2022 03:00 PM
Jessica Wuttke-Campoamor
In Project
3/9/2022 03:09 PM