Need Overview
Need Name:
Rehabilitate Runway
Type:
AIP
Community/Economic Development
M&O Operating
Funding Source:
Select One
State GF
AIP
M&O Operating
Stimulus
N/A
Category:
Select One
Access Road
Airfield
Airport Master Planning
Airside
Apron
ARPA
Building
Building and Equipment (Control Tower)
CARES Act
CRRSA Act
Equipment
Financing
Ground Transportation
Helipad/Heliport
Homes
Land
Landside
Metro Area Planning
Multi Modal
New Airport
Noise
Other
People Mover
Planning
Privatization Planning
Public Building
Rail
Revenue Producing
Runway
Sealane
Seaplane Base
Service/Perimeter Road
State Block Grant Program
State/Regional Planning
Taxilane
Taxiway
Terminal
Sub Category:
Select One
Estimated Cost:
$10,824,270
Description:
The project will resurface the gravel runway, taxiway, access road, and apron (including safety areas). Improvements include airfield lighting, markings, drainage, dust palliative, and visual NAVAIDS. The project is contingent for FFY 2022, but is expected in FFY 2025.
Priority:
Short
Need Origination:
Sponsor
Select One
5010
ALP/Master Plan
Community
FAA Initiatives
Inspection
Letter of Compliance
M&O
Other
Sponsor
State Equipment Fleet (SEF)
Justification:
This airport was relocated in a project that started in 2010. The surfaces currently have areas of subsidence, ponding, and dips due to settlement since the airport’s construction. Resurfacing the operational areas will improve safety and reduce maintenance efforts necessary to keep the airport operational. The runway and taxiway lighting systems are beyond their service lives and need replacement.
Notes:
1/28/2021 CIP Datasheet
Last Edit Date:
3/4/2021 03:18 PM
History Log
Jessica Wuttke-Campoamor
Need Created
3/4/2021 03:11 PM
Jessica Wuttke-Campoamor
In Project
3/4/2021 03:56 PM