Alaska Department of Transportation and Public Facilities
ALASKA AVIATION DATABASE
a component of the
Alaska Aviation System Plan

Need Overview

Need Name: Rehabilitate Runway
Type:
Funding Source:
Category:
Sub Category:
Estimated Cost: $4,710,396
Description: This airport was relocated in 2010. There have not been surface maintenance grants awarded for preventative and preservation maintenance of the operational surfaces since the relocation.
Priority: Mid
Need Origination: Other
Justification: 2021 CIMP Runway and safety areas need preservation maintenance, dust palliative and/or rehabilitation. Lighting system is in very poor condition. REILs and Papis are needed.
Notes: Need originated from CIP datasheet (2019). Rebecca Douglas 6/3/2021 Updated estimated cost from $4,243,600
Last Edit Date: 4/18/2022 05:28 PM