| Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date | Last Verified Date |
|
Equipment, Security, and Fencing: ST EQ SN : Acquire Snow Removal Equipment
Acquire Grader Replacement
|
Short
|
M&O
|
AIP
|
Constructed/Purchased
|
$372,000
| 7/14/2026 | |
|
Equipment, Security, and Fencing: ST EQ SN : Acquire Snow Removal Equipment
Acquire Dozer (Replace 34567)
|
Short
|
Other
|
AIP
|
In Project
|
$387,196
| 7/14/2026 | |
|
Construct Passenger Shelter
Construct Passenger Shelter
|
Long
|
Community
|
N/A
|
Need Created
|
| 4/19/2022 | |
|
Construct Tie-Downs
Construct Tie-Downs
|
Long
|
Community
|
N/A
|
Need Created
|
| 4/19/2022 | |
|
Construct Toilet Facilities
Construct Toilet Facilities
|
Long
|
Community
|
N/A
|
Need Created
|
| 4/19/2022 | |
|
QualityOfLife:Weather Reporting Equipment
Install VWOS System
|
Short
|
FAA Initiatives
|
N/A
|
Need Created
|
| 7/23/2026 | |
|
Access Road: RE AR IM : Rehabilitate Access Road
Rehabilitate Access Road
|
Short
|
Inspection
|
AIP
|
Programmed Need
|
$1,717,000
| 7/14/2026 | |
|
Apron Projects: RE AP IM : Rehabilitate Apron
Rehabilitate Apron
|
Short
|
Inspection
|
AIP
|
Programmed Need
|
$1,654,000
| 7/14/2026 | |
|
Equipment, Security, and Fencing: ST EQ SN : Acquire Snow Removal Equipment
Acquire Loader
|
Mid
|
M&O
|
AIP
|
Programmed Need
|
$500,000
| 1/21/2025 | |
|
Replace Runway Lighting
Replace Runway Lighting
|
Short
|
Inspection
|
AIP
|
Programmed Need
|
$843,000
| 3/9/2022 | |
|
Runway Projects: RC RW IM : Reconstruct Runway
Stabilize Shoulder Erosion
|
Short
|
Inspection
|
N/A
|
Programmed Need
|
$0
| 7/14/2026 | |
|
Runway Projects: RE RW IM : Rehabilitate Runway
Rehabilitate Runway
|
Short
|
Inspection
|
AIP
|
Programmed Need
|
$12,220,000
| 7/14/2026 | |
|
Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
Gravel Resurfacing
|
Short
|
Inspection
|
N/A
|
Programmed Need
|
$0
| 7/14/2026 | |
|
Taxiway Projects: RE TW IM : Rehabilitate Taxiway
Rehabilitate Taxiway
|
Short
|
Inspection
|
AIP
|
Programmed Need
|
$310,000
| 7/14/2026 | |
|
Taxiway Projects: RE TW LI : Rehabilitate Taxiway Lighting
Replace Taxiway Lighting
|
Short
|
Inspection
|
AIP
|
Programmed Need
|
$184,000
| 7/17/2026 | |
| | | | | |
Total
| | |