Apply Dust Palliative
Apply Dust Palliative
|
Short
|
Other
|
AIP
|
In Project
|
$292,085
| 10/4/2021 | |
1 Bay SREB
1 Bay SREB
|
Short
|
Sponsor
|
AIP
|
Need Created
|
$4,243,600
| 9/14/2020 | |
Aeronautical survey
Aeronautical survey
|
Short
|
Community
|
AIP
|
Need Created
|
$0
| 6/10/2022 | |
Construct Passenger Shelter
Construct Passenger Shelter
|
Long
|
Community
|
N/A
|
Need Created
|
| 11/14/2022 | |
Construct Tie-Downs
Construct Tie-Downs
|
Long
|
Community
|
N/A
|
Need Created
|
| 11/14/2022 | |
Construct Toilet Facilities
Construct Toilet Facilities
|
Long
|
Community
|
N/A
|
Need Created
|
| 6/22/2023 | |
Install Misc Navaids
Install Misc Navaids
|
ASAP
|
Sponsor
|
AIP
|
Obligated Need
|
$301,790
| 3/16/2021 | |
Rehabilitate Access Road
Rehabilitate Access Road
|
ASAP
|
Sponsor
|
AIP
|
Obligated Need
|
$1,141,240
| 3/16/2021 | |
Rehabilitate Apron
Rehabilitate Apron
|
ASAP
|
Sponsor
|
AIP
|
Obligated Need
|
$180,250
| 3/16/2021 | |
Rehabilitate Runway
Rehabilitate Runway
|
ASAP
|
Sponsor
|
AIP
|
Obligated Need
|
$817,820
| 11/14/2022 | |
Rehabilitate Taxiway
Rehabilitate Taxiway
|
ASAP
|
Sponsor
|
AIP
|
Obligated Need
|
$43,260
| 3/16/2021 | |
Replace Runway Lighting
Replace Runway Lighting
|
ASAP
|
Sponsor
|
AIP
|
Obligated Need
|
$919,790
| 3/16/2021 | |
Replace Taxiway lighting
Replace Taxiway lighting
|
ASAP
|
Sponsor
|
AIP
|
Obligated Need
|
$345,050
| 3/16/2021 | |
Equipment, Security, and Fencing: ST EQ SN : Acquire Snow Removal Equipment
Acquire Grader (Replace 37713)
|
Mid
|
M&O
|
AIP
|
Programmed Need
|
$500,000
| 1/21/2025 | |
| | | | |
Total
| | |