BIRCHWOOD: Airport Needs List

Filter +/-
Needs Funding Source:
Status:
Need Category:
 
ASAP Needs Total:   Short Term Needs Total:
Mid Term Needs Total: Long Term Needs Total:
All Needs Total: Needs in Project Total:
Number of Needs: Number of Needs in Project:
 
Needs List
NeedsPriorityNeed OriginationFunding SourceStatusEstimated CostLast Edit DateLast Verified Date
Access Road: RE AR IM : Rehabilitate Access Road
Shift Access Road
Mid ALP/Master Plan AIP Need Created $1,583,500 12/31/2025 
Apron Projects: ST AP CO : Construct Apron
Construct Summer Tie-Down / Winter Snow Storage Area
Short ALP/Master Plan AIP Need Created $752,500 12/30/2025 
Apron Projects: ST AP CO : Construct Apron
Construct New General Aviation Apron
Long ALP/Master Plan AIP Need Created $13,490,500 12/31/2025 
Apron Projects: ST AP EX : Expand Apron
Northeast Apron Expansion
Short ALP/Master Plan AIP Need Created $2,903,000 12/30/2025 
Apron Projects: ST AP EX : Expand Apron
Pave Apron Btween Taxiway B and Lease Lots
Mid ALP/Master Plan AIP Need Created $794,500 12/31/2025 
Equipment, Security, and Fencing: ST EQ IN : Install Wind Cone/Segmented Circle
Install Supplemental Wind Cone
Short ALP/Master Plan AIP Need Created $116,500 12/30/2025 
Equipment, Security, and Fencing: ST EQ WX : Install Weather Reporting Equipment
Relocate Weather Station
Short ALP/Master Plan AIP Need Created $599,000 12/31/2025 
Fence: RC FE MS : Reconstruct Perimeter Fencing
Construct New Perimeter Fencing
Short ALP/Master Plan AIP Need Created $381,500 12/30/2025 
Fence: ST FE CO : Install Perimeter Fencing
Perimeter Fencing
Long ALP/Master Plan AIP Need Created $1,370,500 12/31/2025 
Install Continuously Operating Reference Stations (CORS)
Install Continuously Operating Reference Stations (CORS)
Short Sponsor Stimulus Need Created $75,000 3/24/2022 
Land Acquisition (other than noise land): ST LA DV : Acquire Land for Development
Land Acquisition - Runway Protection Zone
Mid ALP/Master Plan AIP Need Created $190,500 12/30/2025 
Land Acquisition (other than noise land): ST LA DV : Acquire Land for Development
Land Acquisition and Avigation Easement
Long ALP/Master Plan AIP Need Created $1,280,500 12/31/2025 
Obstruction removal
Obstruction removal
Short ALP/Master Plan N/A Need Created $253,352 8/23/2021 
Other Projects: CC OT OB : Remove Obstructions
Obstruction Removal from Avigation Easements
Short ALP/Master Plan AIP Need Created $191,500 12/30/2025 
Runway Projects: RC RW IM : Reconstruct Runway
Runway 03G/21G Improvements
Short ALP/Master Plan AIP Need Created $2,731,000 12/30/2025 
Runway Projects: RE RW LI : Rehabilitate Runway Lighting
Rehabilitate Runway 03/21 Edge Lighting
Short ALP/Master Plan AIP Need Created $2,712,500 12/30/2025 
Runway Projects: ST RW IN : Install Instrument Approach Aid
Install PAPI on Runway 03/21
Short ALP/Master Plan AIP Need Created $539,500 12/30/2025 
Taxiway Projects: EN TW CO : Construct Taxiway
Taxiway F Construct Connecting
ALP/Master Plan AIP Need Created $972,500 12/30/2025 
Taxiway Projects: SA TW IM : Realign Taxiway
Taxiway A Remove for Shift
Short ALP/Master Plan AIP Need Created $415,000 12/30/2025 
Taxiway Projects: ST TW EX : Extend/Expand Taxiway
Taxiway A - Construct New
Short ALP/Master Plan AIP Need Created $715,000 7/17/2026 
Taxiway Projects: ST TW EX : Extend/Expand Taxiway
Construct Taxiway A Extension
Long ALP/Master Plan AIP Need Created $525,000 12/31/2025 
Taxiway Projects: ST TW SH : Shift Taxiway
Taxiway D Shift
Short ALP/Master Plan AIP Need Created $1,123,500 12/30/2025 
Taxiway Projects: ST TW SH : Shift Taxiway
Taxiway E Removal
Short ALP/Master Plan AIP Need Created $181,500 12/30/2025 
Apron Projects: RS AP IM : Reseal Apron Pavement
Painted Markings & Crack Seal 2029
Mid M&O AIP Programmed Need $25,000 1/26/2026 
Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
Painted Markings & Crack Seal 2029
Mid M&O AIP Programmed Need $150,000 1/26/2026 
Taxiway Projects: RS TW IM : Reseal Taxiway Pavement
Painted Markings & Crack Seal 2029
Mid M&O AIP Programmed Need $50,000 1/26/2026 
Conduct Airport Master Plan Update Stage 2
Conduct Airport Master Plan Update Stage 2
Short Community AIP Obligated Need $250,000 8/10/2026 
Equipment, Security, and Fencing: ST EQ SN : Acquire Snow Removal Equipment
Acquire Grader
Short M&O AIP Obligated Need $400,000 9/4/2026 
Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
Pavement Marking & Crack Seal
Short M&O AIP Obligated Need $159,375 7/14/2026 
Equipment, Security, and Fencing: ST EQ SN : Acquire Snow Removal Equipment
Aqcuire New Loader & Snowblower Attachment
Short State Equipment Fleet (SEF) AIP Constructed/Purchased $650,000 7/14/2026 
      Total