Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date | Last Verified Date |
Aqcuire New Loader & Snowblower Attachment
Aqcuire New Loader & Snowblower Attachment
|
Short
|
State Equipment Fleet (SEF)
|
AIP
|
In Project
|
$650,000
| 10/12/2022 | |
Conduct Airport Master Plan Update Stage 2
Conduct Airport Master Plan Update Stage 2
|
Short
|
Community
|
AIP
|
In Project
|
$250,000
| 1/19/2022 | |
Install Continuously Operating Reference Stations (CORS)
Install Continuously Operating Reference Stations (CORS)
|
Short
|
Sponsor
|
Stimulus
|
Need Created
|
$75,000
| 3/24/2022 | |
Obstruction removal
Obstruction removal
|
Short
|
ALP/Master Plan
|
N/A
|
Need Created
|
$238,809
| 8/23/2021 | |
Pavement Marking & Crack Seal
Pavement Marking & Crack Seal
|
Short
|
M&O
|
AIP
|
Obligated Need
|
$159,375
| 1/22/2023 | |
| | | | |
Total
| | |