| Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date | Last Verified Date |
|
Construct Passenger Shelter
Construct Passenger Shelter
|
Long
|
Community
|
N/A
|
Need Created
|
| 1/19/2023 | |
|
Construct Tie-Downs
Construct Tie-Downs
|
Long
|
Community
|
N/A
|
Need Created
|
| 1/19/2023 | |
|
Construct Toilet Facilities
Construct Toilet Facilities
|
Long
|
Community
|
N/A
|
Need Created
|
| 1/19/2023 | |
|
QualityOfLife:FAA Weather Camera
Install Weather Cameras
|
Short
|
Other
|
N/A
|
Need Created
|
| 7/21/2026 | |
|
QualityOfLife:Weather Reporting Equipment
Install AWOS System
|
Short
|
FAA Initiatives
|
N/A
|
Need Created
|
| 7/21/2026 | |
|
Construct SREB
Construct SREB
|
Mid
|
M&O
|
AIP
|
Obligated Need
|
$2,440,000
| 4/4/2023 | |
|
Equipment, Security, and Fencing: ST EQ IN : Install Wind Cone/Segmented Circle
Install Miscellaneous NAVAIDs
|
Mid
|
M&O
|
AIP
|
Obligated Need
|
$193,000
| 7/20/2026 | |
|
Rehabilitate Runway, Taxiway, Apron & Access Road
Rehabilitate Runway, Taxiway, Apron & Access Road
|
Mid
|
M&O
|
AIP
|
Obligated Need
|
$4,155,000
| 4/4/2023 | |
|
Replace Runway & Taxiway Lighting
Replace Runway & Taxiway Lighting
|
Mid
|
M&O
|
AIP
|
Obligated Need
|
$729,000
| 4/4/2023 | |
|
Equipment, Security, and Fencing: ST EQ SN : Acquire Snow Removal Equipment
Acquire Loader with Attachments (Replace 41535)
|
Short
|
Other
|
AIP
|
Constructed/Purchased
|
$442,840
| 7/21/2026 | |
| | | | | |
Total
| | |