| Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date | Last Verified Date | 
					| Acquire replacement water rescue rafts
                        
                            Acquire replacement water rescue rafts | Short | Letter of Compliance | AIP | In Project | $36,392 | 3/17/2021 |  | 
					| Acquire Snow Blower MB
                        
                            Acquire Snow Blower MB | Short | M&O | AIP | In Project | $328,125 | 1/22/2023 |  | 
					| Construct 6,721' Full Parallel Taxiway
                        
                            Construct 6,721' Full Parallel Taxiway | Long | Community | AIP | In Project | $33,630,144 | 11/23/2015 |  | 
					| Gate Replacements and Security Upgrades
                        
                            Gate Replacements and Security Upgrades | Short | Inspection | AIP | In Project | $7,536,304 | 10/2/2023 |  | 
					| Master Plan Update
                        
                            Master Plan Update | Short | Other | AIP | In Project | $636,540 | 11/20/2020 |  | 
					| Pave the Parking Lot
                        
                            Pave the Parking Lot | Mid | Community | AIP | Need Created | $5,000,000 | 2/18/2022 |  | 
					| Runway Projects: SA RW OB : Obstruction Marking/Lighting/Removal (Hazard)
                        
                            Obstruction Removal (2025) | Short | M&O | AIP | Need Created | $455,000 | 4/8/2025 |  | 
					| Construct Tie-Downs
                        
                            Construct Tie-Downs | Long | Community | N/A | Need Created |  | 8/19/2022 |  | 
					| Acquire Loader
                        
                            Acquire Loader | Short | M&O | AIP | Obligated Need | $431,250 | 1/22/2023 |  | 
					| Equipment, Security, and Fencing: RE EQ SN : Rehabilitate Snow Removal Equipment
                        
                            MB5 Plow truck and Cradle broom | Mid | M&O | AIP | Obligated Need | $935,451 | 4/8/2025 |  | 
					| Procure AFFF Testing Equipment
                        
                            Procure AFFF Testing Equipment | ASAP | FAA Initiatives | AIP | Obligated Need | $24,000 | 7/12/2023 |  | 
					| Runway: RS RW IM: Reseal/Resurface Runway Pavement
                        
                            Pavement Markings | Short | Inspection | AIP | Obligated Need | $206,000 | 9/3/2024 |  | 
					| Construct New SRE/ARFF Building
                        
                            Construct New SRE/ARFF Building | Short | Other | AIP | Programmed Need | $1,520,121 | 3/2/2021 |  | 
					| Construct Sand and Chemical Building
                        
                            Construct Sand and Chemical Building | Short | Other | AIP | Programmed Need | $2,153,505 | 6/19/2015 |  | 
					| Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
                        
                            Pavement Markings (2028) | Mid | M&O | AIP | Programmed Need | $200,000 | 2/7/2025 |  | 
					| Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
                        
                            Pavement Marking & Crack Seal (2027) | Mid | M&O | AIP | Programmed Need | $200,000 | 9/17/2025 |  | 
					| Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
                        
                            Pavement Marking & Crack Seal (2028) | Mid | M&O | AIP | Programmed Need | $200,000 | 9/17/2025 |  | 
					| Runway Projects: SA RW OB : Obstruction Marking/Lighting/Removal (Hazard)
                        
                            Obstruction removal north end of RW 11-29 (2027) | Mid | M&O | AIP | Programmed Need | $1,066,714 | 4/8/2025 |  | 
					|  |  |  |  |  | Total |  |  |