SELAWIK: Airport Needs List

Filter +/-
Needs Funding Source:
Status:
Need Category:
 
ASAP Needs Total:   Short Term Needs Total:
Mid Term Needs Total: Long Term Needs Total:
All Needs Total: Needs in Project Total:
Number of Needs: Number of Needs in Project:
 
Needs List
NeedsPriorityNeed OriginationFunding SourceStatusEstimated CostLast Edit DateLast Verified Date
Conduct Airport Master Plan Update
Conduct Airport Master Plan Update
Long Other AIP In Project $772,500 2/9/2021 
Construct SRE Building
Construct SRE Building
Short Inspection AIP In Project $2,251,017 3/16/2022 
Equipment, Security, and Fencing: ST EQ IN : Install Wind Cone/Segmented Circle
Replace Wind Cones, Segmented Circle and Beacon
Short Inspection AIP In Project $225,101 7/20/2026 
Extend Runway 4/22 to 3,300'
Extend Runway 4/22 to 3,300'
Long Other AIP In Project $11,500,000 3/16/2022 
Extend Runway 9/27 RSA
Extend Runway 9/27 RSA
Short Other AIP In Project $11,500,000 3/16/2022 
Reconstruct Runway Lighting
Reconstruct Runway Lighting
Short Other AIP In Project $1,000,000 3/16/2022 
Reconstruct Taxiway Lighting
Reconstruct Taxiway Lighting
Short Other AIP In Project $350,000 3/16/2022 
Rehabilitate Apron
Rehabilitate Apron
Mid Other AIP In Project $3,850,000 3/16/2022 
Rehabilitate Runway 4/22
Rehabilitate Runway 4/22
Mid Other AIP In Project $6,500,000 3/16/2022 
Rehabilitate Runway 9/27
Rehabilitate Runway 9/27
Mid Other AIP In Project $6,500,000 3/16/2022 
Rehabilitate Taxiways
Rehabilitate Taxiways
Mid Other AIP In Project $6,000,000 3/16/2022 
Update ALP
Update ALP
Short Other AIP In Project $0 3/16/2022 
Acquire Loader (Replace #35026)
Acquire Loader (Replace #35026)
Mid M&O AIP Need Created $450,000 4/10/2024 
Construct Passenger Shelter
Construct Passenger Shelter
Long Community N/A Need Created 4/28/2022 
Construct Tie-Downs
Construct Tie-Downs
Long Community N/A Need Created 4/28/2022 
Construct Toilet Facilities
Construct Toilet Facilities
Long Community N/A Need Created 4/28/2022 
Acquire Loader
Acquire Loader
Mid M&O AIP Obligated Need $460,000 3/13/2023 
Acquire Grader (Replace #35071)
Acquire Grader (Replace #35071)
Mid M&O AIP Programmed Need $490,000 6/9/2026 
Acquire New Dozer
Acquire New Dozer
Short M&O AIP Programmed Need $407,813 6/9/2026 
      Total   