KALTAG: Airport Needs List

Base Information
Owner: ALASKA DOT&PF NORTHERN REGION
NPIAS: 02-0137
Airport Use: Public
Type: Airport
FAA Associated City: KALTAG
DOT&PF Region: Northern
DOT Owned: True
Facility Status: Active
Filter +/-
Needs Funding Source:
Status:
Need Category:
M&O Activity:
 
ASAP Needs Total:   Short Term Needs Total:
Mid Term Needs Total: Long Term Needs Total:
All Needs Total: Needs in Project Total:
Number of Needs: Number of Needs in Project:
 
Needs List
NeedsPriorityNeed OriginationFunding SourceStatusEstimated CostLast Edit DateLast Verified Date
Acquire Dozer (Replace #38904)
Acquire Dozer (Replace #38904)
Long M&O AIP In Project $440,000 4/11/2024 
Apply Dust Palliative
Apply Dust Palliative
Short Inspection AIP In Project $228,330 1/13/2016 
Construct SRE Building
Construct SRE Building
Short Other AIP In Project $1,449,091 2/17/2021 
Construct Ultimate Access Road
Construct Ultimate Access Road
N/A ALP/Master Plan AIP In Project $3,653,361 6/19/2015 
Drainage Improvements
Drainage Improvements
Short Inspection AIP In Project $106,090 3/14/2019 
Install New Wind Cone
Install New Wind Cone
Short Inspection AIP In Project $19,567 6/19/2015 
Kaltag SREB Replacement
Kaltag SREB Replacement
Mid Other AIP In Project $2,970,520 3/15/2019 
Replace Airport Lighting System
Replace Airport Lighting System
Mid Other AIP In Project $927,418 2/17/2021 
Replace Segmented Circle
Replace Segmented Circle
Short Inspection AIP In Project $71,759 3/14/2019 
Stage 1 - Rehabilitate Runway 3/21
Stage 1 - Rehabilitate Runway 3/21
Mid Other AIP In Project $5,150,000 2/17/2021 
Other Projects: OT CC OB : Remove Obstructions
Brush Cutting
Short Other AIP Need Created $0 4/7/2026 
Rehabilitate Runway Dust Palliative
Rehabilitate Runway Dust Palliative
Long FAA Initiatives AIP Need Created $800,000 1/10/2024 
Construct Passenger Shelter
Construct Passenger Shelter
Long Community N/A Need Created 2/27/2023 
Construct Toilet Facilities
Construct Toilet Facilities
Long Other N/A Need Created 2/27/2023 
Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
Resurface & Apply Dust Palliative 2029
Mid M&O AIP Programmed Need $410,000 1/27/2026 
      Total   
Needs List Process Flow