| Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date | Last Verified Date |
|
Runway: RS RW IM: Reseal/Resurface Runway Pavement
Gravel Resurfacing
|
Short
|
Inspection
|
AIP
|
Draft Need
|
$350,000
| 8/1/2024 | |
|
Other Projects: OT CC OB : Remove Obstructions
Brush Cutting
|
Short
|
Other
|
AIP
|
Need Created
|
$0
| 4/7/2026 | |
|
QualityOfLife:Weather Reporting Equipment
Install VWOS
|
ASAP
|
FAA Initiatives
|
N/A
|
Need Created
|
| 8/5/2026 | |
|
Nanwalek/Port Graham Airport Relocation - Stage 2
Nanwalek/Port Graham Airport Relocation - Stage 2
|
Long
|
Other
|
AIP
|
In Project
|
$15,450,000
| 2/17/2021 | |
|
Nanwalek/Port Graham Airport Relocation - Stage 3
Nanwalek/Port Graham Airport Relocation - Stage 3
|
Long
|
Other
|
AIP
|
In Project
|
$4,841,000
| 2/17/2021 | |
|
Equipment, Security, and Fencing: ST EQ SN : Acquire Snow Removal Equipment
Acquire Grader
|
Mid
|
M&O
|
AIP
|
Programmed Need
|
$500,000
| 8/27/2025 | |
|
Nanwalek/Port Graham Airport Relocation - Stage 1
Nanwalek/Port Graham Airport Relocation - Stage 1
|
Long
|
Other
|
AIP
|
Programmed Need
|
$15,450,000
| 2/17/2021 | |
|
Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
Apply Dust Palliative
|
Short
|
M&O
|
AIP
|
Constructed/Purchased
|
$109,000
| 8/14/2026 | |
| | | | | |
Total
| | |