Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date | Last Verified Date |
Apply Dust Palliative
Apply Dust Palliative
|
N/A
|
M&O
|
AIP
|
In Project
|
$1,125,508
| 11/29/2019 | |
Replace airport signage
Replace airport signage
|
Short
|
Sponsor
|
AIP
|
In Project
|
$1,000,000
| 3/21/2024 | |
Replace runway lighting
Replace runway lighting
|
Short
|
Sponsor
|
AIP
|
In Project
|
$800,000
| 3/21/2024 | |
Replace Segmented Circle and windsock
Replace Segmented Circle and windsock
|
Short
|
Sponsor
|
AIP
|
In Project
|
$500,000
| 3/21/2024 | |
Replace taxiway lights
Replace taxiway lights
|
Short
|
Sponsor
|
AIP
|
In Project
|
$300,000
| 3/21/2024 | |
Resurface Apron
Resurface Apron
|
Short
|
Sponsor
|
AIP
|
In Project
|
$1,000,000
| 3/21/2024 | |
Resurface runway
Resurface runway
|
Short
|
Sponsor
|
AIP
|
In Project
|
$5,000,000
| 3/21/2024 | |
Resurface taxiway
Resurface taxiway
|
Short
|
Sponsor
|
AIP
|
In Project
|
$1,000,000
| 3/21/2024 | |
Visual aid replacement
Visual aid replacement
|
Short
|
Inspection
|
AIP
|
In Project
|
$1,060,900
| 11/29/2019 | |
Construct Passenger Shelter
Construct Passenger Shelter
|
Long
|
Community
|
N/A
|
Need Created
|
| 2/27/2023 | |
Construct Toilet Facilities
Construct Toilet Facilities
|
Long
|
Community
|
N/A
|
Need Created
|
| 2/27/2023 | |
| | | | |
Total
| | |