| Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date | Last Verified Date |
|
Construct Passenger Shelter
Construct Passenger Shelter
|
Long
|
Community
|
N/A
|
Need Created
|
| 12/22/2022 | |
|
Construct Toilet Facilities
Construct Toilet Facilities
|
Long
|
Community
|
N/A
|
Need Created
|
| 12/22/2022 | |
|
Apron Projects: RE AP IM : Rehabilitate Apron
Rehabilitate Apron
|
Short
|
Inspection
|
AIP
|
Programmed Need
|
$943,000
| 7/21/2026 | |
|
Apron Projects: ST AP CO : Construct Apron
Construct New Apron
|
Mid
|
Other
|
AIP
|
Programmed Need
|
$1,000,000
| 7/21/2026 | |
|
Construct 1,465' Runway Extension
Construct 1,465' Runway Extension
|
Long
|
Community
|
AIP
|
Programmed Need
|
$14,336,191
| 11/23/2015 | |
|
Construct 2, 1-bay SREBs
Construct 2, 1-bay SREBs
|
Short
|
Other
|
AIP
|
Programmed Need
|
$2,318,547
| 2/12/2021 | |
|
Equipment, Security, and Fencing: ST EQ SN : Acquire Snow Removal Equipment
Acquire Loader
|
Short
|
M&O
|
AIP
|
Programmed Need
|
$500,000
| 8/27/2025 | |
|
Install MIRL Runway Lighting
Install MIRL Runway Lighting
|
Long
|
Community
|
AIP
|
Programmed Need
|
$1,076,433
| 11/23/2015 | |
|
Install Taxiway Lighting
Install Taxiway Lighting
|
Mid
|
Other
|
AIP
|
Programmed Need
|
$515,000
| 2/12/2021 | |
|
Land Acquisition (other than noise land): ST LA DV : Acquire Land for Development
Acquire Native Allotments and Tribal Property
|
Long
|
Sponsor
|
AIP
|
Programmed Need
|
$1,323,888
| 7/17/2026 | |
|
Runway Projects: RE RW IM : Rehabilitate Runway
Rehabilitate Runway
|
Short
|
Inspection
|
AIP
|
Programmed Need
|
$13,454,000
| 7/21/2026 | |
|
Taxiway Projects: RE TW IM : Rehabilitate Taxiway
Rehabilitate Taxiway
|
ASAP
|
M&O
|
AIP
|
Programmed Need
|
$1,000,000
| 7/21/2026 | |
| | | | | |
Total
| | |