ASAP Needs Total: $0   Short Term Needs Total: $32,662,762
Mid Term Needs Total: $630,000 Long Term Needs Total:
All Needs Total: $33,292,762 Needs in Project Total: $33,292,762
Number of Needs: 12 Number of Needs in Project: 11
 
Needs List
NeedsPriorityNeed OriginationFunding SourceStatusEstimated CostLast Edit DateLast Verified Date
ALP update and wind study ALP update and wind study Mid Sponsor AIP In Project $630,000 5/25/2022 
Construct SREB Construct SREB Short Other AIP In Project $3,922,147 1/20/2023 
Expand Apron Expand Apron Short Other AIP In Project $86,903 1/20/2023 
Extend Runway Safety Area Extend Runway Safety Area Short Inspection AIP In Project $20,231,164 1/20/2023 
Rehabilitate Apron Rehabilitate Apron Short Other AIP In Project $962,128 1/20/2023 
Rehabilitate Runway Rehabilitate Runway Short Inspection AIP In Project $5,282,221 9/25/2020 
Rehabilitate Taxiway Rehabilitate Taxiway Short Inspection AIP In Project $376,044 1/20/2023 
Runway Lighting Runway Lighting Short Inspection AIP In Project $630,174 9/25/2020 
Taxiway Lighting Taxiway Lighting Short Inspection AIP In Project $178,231 9/25/2020 
Construct Passenger Shelter Construct Passenger Shelter Long Community N/A Need Created 1/20/2023 
Acquire New Grader Acquire New Grader Short Other AIP Obligated Need $431,250 1/20/2023 
Acquire New Loader Acquire New Loader Short M&O AIP Obligated Need $562,500 1/20/2023 
      Total $33,292,762