YAKUTAT: Airport Needs List

Filter +/-
Needs Funding Source:
Status:
Need Category:
 
ASAP Needs Total:   Short Term Needs Total:
Mid Term Needs Total: Long Term Needs Total:
All Needs Total: Needs in Project Total:
Number of Needs: Number of Needs in Project:
 
Needs List
NeedsPriorityNeed OriginationFunding SourceStatusEstimated CostLast Edit DateLast Verified Date
Airport Perimeter Fence
Airport Perimeter Fence
Short Inspection AIP In Project $16,390,905 11/20/2020 
Apron Projects: ST AP EX : Expand Apron
Pave DOT Building Area
ASAP M&O AIP In Project $0 7/17/2026 
Brush Cutting
Brush Cutting
N/A M&O State GF In Project $130,474 9/17/2015 
Gate Card Reader Systems
Gate Card Reader Systems
Short Sponsor AIP In Project $2,500,000 5/24/2022 
Gate Replacements and Security Upgrades
Gate Replacements and Security Upgrades
Short Inspection AIP In Project $3,090,000 12/20/2021 
Gate Upgrades
Gate Upgrades
Short M&O AIP In Project $2,500,000 5/24/2022 
Overhead Lighting Apron A
Overhead Lighting Apron A
ASAP M&O AIP In Project $0 11/14/2023 
Repair Sections of Fence
Repair Sections of Fence
Short Sponsor AIP In Project $1,500,000 5/24/2022 
Repave Apron B
Repave Apron B
M&O AIP In Project $0 11/14/2023 
Repave TXY A1
Repave TXY A1
M&O AIP In Project $0 11/14/2023 
Install Continuously Operating Reference Stations (CORS)
Install Continuously Operating Reference Stations (CORS)
Short Sponsor Stimulus Need Created $75,000 3/24/2022 
Repave TXY D
Repave TXY D
ASAP M&O AIP Need Created $0 11/14/2023 
Wildlife Detection System
Wildlife Detection System
Short Letter of Compliance AIP Need Created $2,100,000 1/31/2024 
Construct Tie-Downs
Construct Tie-Downs
Long Community N/A Need Created 9/12/2022 
Construct Toilet Facilities
Construct Toilet Facilities
Long Community N/A Need Created 9/12/2022 
Airport Master Planning: PL MA UP : Update Airport Master Plan
Update Airport Master Plan
Short Sponsor AIP Obligated Need $1,000,000 7/17/2026 
Equipment, Security, and Fencing: SA EQ AQ : Acquire Aircraft Rescue and Fire Fighting Safety Equipment
Acquire replacement water rescue rafts
Short Letter of Compliance AIP Obligated Need $36,392 7/15/2026 
Equipment: ST EQ SN: Acquire Snow Removal Equipment
Yakutat Blower
Short M&O AIP Obligated Need $1,000,000 9/27/2024 
Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
Pavement Markings
Short M&O AIP Obligated Need $284,000 7/20/2026 
Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
Pavement Markings (2028)
Short M&O AIP Obligated Need $300,000 7/17/2026 
Yakutat Loader Whl 4.5-5 CY
Yakutat Loader Whl 4.5-5 CY
ASAP Other AIP Obligated Need $463,500 4/19/2021 
Apron Drainage Rebuild
Apron Drainage Rebuild
Short Other AIP Programmed Need $6,180,000 2/1/2021 
Equipment, Security, and Fencing: SA EQ RF : Acquire Aircraft Rescue & Fire Fighting Vehicle
Replace ARFF Truck (38269)
Mid M&O AIP Programmed Need $1,200,000 7/20/2026 
Rehabilitate apron
Rehabilitate apron
Short Community AIP Programmed Need $5,150,000 2/1/2021 
Runway Projects: RE RW IM : Rehabilitate Runway
Painted Markings 2029
Long M&O AIP Programmed Need $130,000 1/20/2026 
Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
Pavement Markings (2027)
Mid M&O AIP Programmed Need $120,000 9/17/2025 
Runway Projects: RS RW IM : Reseal/Resurface Runway Pavement
Pavement Markings (2028)
Mid M&O AIP Programmed Need $120,000 9/17/2025 
Runway: ST RW OB: Obstruction Marking\Lighting\Removal
Obstruction Removal
Mid Other AIP Programmed Need $500,000 11/27/2024 
      Total   
Needs List Process Flow