Needs | Priority | Need Origination | Funding Source | Status | Estimated Cost | Last Edit Date | Last Verified Date |
Acquire replacement water rescue rafts
Acquire replacement water rescue rafts
|
Short
|
Letter of Compliance
|
AIP
|
In Project
|
$36,392
| 3/17/2021 | |
Airport Perimeter Fence
Airport Perimeter Fence
|
Short
|
Inspection
|
AIP
|
In Project
|
$16,390,905
| 11/20/2020 | |
Apron Drainage Rebuild
Apron Drainage Rebuild
|
Short
|
Other
|
AIP
|
In Project
|
$6,180,000
| 2/1/2021 | |
Brush Cutting
Brush Cutting
|
N/A
|
M&O
|
State GF
|
In Project
|
$122,985
| 9/17/2015 | |
Gate Card Reader Systems
Gate Card Reader Systems
|
Short
|
Sponsor
|
AIP
|
In Project
|
$2,500,000
| 5/24/2022 | |
Gate Replacements and Security Upgrades
Gate Replacements and Security Upgrades
|
Short
|
Inspection
|
AIP
|
In Project
|
$3,090,000
| 12/20/2021 | |
Gate Upgrades
Gate Upgrades
|
Short
|
M&O
|
AIP
|
In Project
|
$2,500,000
| 5/24/2022 | |
Overhead Lighting Apron A
Overhead Lighting Apron A
|
ASAP
|
M&O
|
AIP
|
In Project
|
$0
| 11/14/2023 | |
Pave DOT building area
Pave DOT building area
|
ASAP
|
M&O
|
AIP
|
In Project
|
$0
| 11/14/2023 | |
Rehabilitate apron
Rehabilitate apron
|
Short
|
Community
|
AIP
|
In Project
|
$5,150,000
| 2/1/2021 | |
Repair Sections of Fence
Repair Sections of Fence
|
Short
|
Sponsor
|
AIP
|
In Project
|
$1,500,000
| 5/24/2022 | |
Repave Apron B
Repave Apron B
|
|
M&O
|
AIP
|
In Project
|
$0
| 11/14/2023 | |
Repave TXY A1
Repave TXY A1
|
|
M&O
|
AIP
|
In Project
|
$0
| 11/14/2023 | |
Crack Seal
Crack Seal
|
Short
|
M&O
|
AIP
|
Need Created
|
$140,625
| 12/22/2023 | |
Install Continuously Operating Reference Stations (CORS)
Install Continuously Operating Reference Stations (CORS)
|
Short
|
Sponsor
|
Stimulus
|
Need Created
|
$75,000
| 3/24/2022 | |
Install signs on RWY 11/29
Install signs on RWY 11/29
|
ASAP
|
M&O
|
AIP
|
Need Created
|
$0
| 11/14/2023 | |
Repave TXY D
Repave TXY D
|
ASAP
|
M&O
|
AIP
|
Need Created
|
$0
| 11/14/2023 | |
Wildlife Detection System
Wildlife Detection System
|
Short
|
Letter of Compliance
|
AIP
|
Need Created
|
$2,100,000
| 1/31/2024 | |
Construct Tie-Downs
Construct Tie-Downs
|
Long
|
Community
|
N/A
|
Need Created
|
| 9/12/2022 | |
Construct Toilet Facilities
Construct Toilet Facilities
|
Long
|
Community
|
N/A
|
Need Created
|
| 9/12/2022 | |
Pavement Markings
Pavement Markings
|
Short
|
M&O
|
AIP
|
Obligated Need
|
$284,000
| 1/27/2022 | |
Procure AFFF Testing Equipment
Procure AFFF Testing Equipment
|
ASAP
|
FAA Initiatives
|
AIP
|
Obligated Need
|
$24,000
| 7/12/2023 | |
Yakutat Loader Whl 4.5-5 CY
Yakutat Loader Whl 4.5-5 CY
|
ASAP
|
Other
|
AIP
|
Obligated Need
|
$463,500
| 4/19/2021 | |
Equipment: SA EQ RF: Acquire Aircraft Rescue and Fire Fighting Vehicle
Replace ARFF Truck (38269)
|
Mid
|
M&O
|
AIP
|
Programmed Need
|
$1,200,000
| 11/27/2024 | |
Equipment: ST EQ SN: Acquire Snow Removal Equipment
Yakutat Blower
|
Short
|
M&O
|
AIP
|
Programmed Need
|
$1,000,000
| 9/27/2024 | |
Planning: CC PL UP: Update Airport Master Plan Study
Update Airport Master Plan
|
Short
|
Sponsor
|
AIP
|
Programmed Need
|
$1,000,000
| 9/27/2024 | |
Runway: ST RW OB: Obstruction Marking\Lighting\Removal
Obstruction Removal
|
Mid
|
Other
|
AIP
|
Programmed Need
|
$500,000
| 11/27/2024 | |
| | | | |
Total
| | |